The Karachi Water and Sewerage Corporation (KWSC) says water supply to the city has been fully restored after annual maintenance at the Dhabeji pumping station. All 21 pumps are now running.
Work completed
- Dhabeji: a new 60-inch valve installed, pump houses and operating system maintained, valve on Line No. 1 repaired
- Pipri: annual maintenance of all pump houses and repairs to the operating system
- Shahrah-e-Bhutto: about 150 feet of 32-inch pipeline replaced and a new butterfly valve fitted
- Haleji Conduit: a leak repaired
If your area is still dry
It can take a day or two for pressure to return to tail-end areas. Residents still facing shortages can register a complaint with KWSC’s helpline 1339.